Standards & compliance · Compliance
EN ISO 5817 — Weld Inspection Levels

Quick answer
EN ISO 5817 grades weld imperfections in levels B, C and D — stringent, intermediate and moderate. Level C is the level commonly paired with EN 1090 EXC2 structural work. The level belongs in the project specification: it decides what an inspector accepts, and arguing about it after fabrication is too late.
In detail
Name the level in the purchase specification alongside the execution class.
NDT extent (visual, magnetic particle, ultrasonic) is specified with the level.
| Item | What it is | Note |
|---|---|---|
| Level B | Stringent | Highest demand |
| Level C | Intermediate | Typical EXC2 pairing |
| Level D | Moderate | Low consequence |
Specifying this on your project
Specify this standard in the enquiry by the items in the table above — Level B, Level C, Level D — naming the level, class or certificate type your project requires, and the quotation is built and documented to exactly that. Leave it unnamed and the specification is argued about at inspection instead. The certifications page explains which documents are available on request.
Primary sources
This page rests on the primary sources below — the code authority, the regulator's own platform, the standards body. Check the claim at its source.
Questions buyers ask
FAQ
Are you a factory or a trading company?
HANJI Steel Structures is operated by Jiangsu Hanji Supply Chain Co., Ltd. — design and fabrication are our own work, from Cangzhou, Hebei. Products outside our line (specialist doors, refrigeration, fit-out) are named in the scope as coordinated supply.
Can I inspect before shipment?
Yes — your own visit or a third-party inspector (SGS, Bureau Veritas) at agreed hold points, before the balance is paid.