Our Process — from requirement to site handover in nine steps

Quick answer
Every order runs the same nine steps: submit requirements, quotation, deposit, design and approval drawings, production plan, fabrication with inspection hold points, packing, balance and shipment, and installation guidance. The steps are the contract's skeleton — payment stages attach to verifiable events inside them, never to dates alone.
The nine steps
- 1 · Submit the RFQ — drawings or BOQ, dimensions, load basis, destination port, crane and cladding scope (the brief builder collects the same inputs)
- 2 · Quotation — itemised by scope line, with tonnage, kg/m² and validity stated
- 3 · Deposit — against the signed contract; design starts
- 4 · Design — approval drawings, then shop drawings; foundation reactions issued
- 5 · Production plan — material procurement against mill certificates; line schedule fixed
- 6 · Fabrication — the nine-process H-beam line, with inspection hold points open to third parties
- 7 · Packing — bundles in erection sequence, packing list matched to drawings
- 8 · Balance & shipment — after inspection; bill of lading and document pack issued
- 9 · Installation guidance — erection drawings, remote support, supervision available overseas
Where time actually goes
Engineering 1–3 weeks and fabrication 2–5 weeks are the controllable stages (Laotie shipping guide). Approvals and certificates — SBC review, SABER product and shipment certificates — run in parallel when they are planned at step 2 and become the critical path when they are remembered at step 8.
Questions buyers ask
FAQ
Are you a factory or a trading company?
HANJI Steel Structures is operated by Jiangsu Hanji Supply Chain Co., Ltd. — design and fabrication are our own work, from Cangzhou, Hebei. Products outside our line (specialist doors, refrigeration, fit-out) are named in the scope as coordinated supply.
Can I inspect before shipment?
Yes — your own visit or a third-party inspector (SGS, Bureau Veritas) at agreed hold points, before the balance is paid.
What does the price for an order include?
Only what its scope line says: scope (frame, envelope or turnkey), basis (FOB, CIF or installed) and date are stated on every figure — the FOB vs CIF guide explains the ladder.