Quick answer

Buildings ship as labelled bundles in 40 ft containers, packed in erection sequence. From Qingdao: Dammam 22–28 days, Jeddah 24–30 days; Southeast Asia 1–2 weeks, the Middle East 2–3 weeks and Africa 3–5 weeks by sea. Structures classify under HS 9406.10 / 7308.90 with GCC duty typically 5%.

Transit times by destination

DestinationPortSea time
Saudi ArabiaDammam22–28 days from Qingdao
Saudi ArabiaJeddah24–30 days from Qingdao
UAE / Oman / Qatar / KuwaitJebel Ali · Sohar · Hamad · Shuwaikh2–3 weeks (Middle East)
Egypt / Kenya / NigeriaSokhna · Mombasa · Lagos3–5 weeks (Africa)
Southeast AsiaManila · HCMC · Bangkok · Jakarta1–2 weeks

Packing is a design output

Member lengths, nesting and bundle design decide the container count — which is why freight belongs inside the quotation. Bundles are packed in erection sequence and every bundle identity matches the packing list and the erection drawings, so the site unloads in the order it builds.

Questions buyers ask

FAQ

Are you a factory or a trading company?

HANJI Steel Structures is operated by Jiangsu Hanji Supply Chain Co., Ltd. — design and fabrication are our own work, from Cangzhou, Hebei. Products outside our line (specialist doors, refrigeration, fit-out) are named in the scope as coordinated supply.

Can I inspect before shipment?

Yes — your own visit or a third-party inspector (SGS, Bureau Veritas) at agreed hold points, before the balance is paid.