Quick answer

A steel building kit quotation needs the building inputs — dimensions, destination, crane if any, cladding scope (HF Steel quotation guides) — plus the kit questions: who erects, what already exists on site, and what must arrive in the first container. Kit pricing is logistics as much as steel; the destination port and the erection plan are price inputs.

In detail

Tell us what local supply covers — concrete, crane hire, crew — so the kit boundary is drawn where your market is actually cheaper.

Phased delivery (frame first, cladding following) is a quotation option; it changes container count and cash flow, not just dates.

Questions buyers ask

FAQ

Are you a factory or a trading company?

HANJI Steel Structures is operated by Jiangsu Hanji Supply Chain Co., Ltd. — design and fabrication are our own work, from Cangzhou, Hebei. Products outside our line (specialist doors, refrigeration, fit-out) are named in the scope as coordinated supply.

Can I inspect before shipment?

Yes — your own visit or a third-party inspector (SGS, Bureau Veritas) at agreed hold points, before the balance is paid.

What does the price for a steel building kit include?

Only what its scope line says: scope (frame, envelope or turnkey), basis (FOB, CIF or installed) and date are stated on every figure — the FOB vs CIF guide explains the ladder.