How long does it take to build a steel warehouse?

Quick answer
A steel warehouse runs about 5–10 weeks order-to-site: engineering 1–3 weeks, fabrication 2–5 weeks, then sea freight — 22–28 days Qingdao to Dammam, 24–30 to Jeddah (Laotie). Erection of a standard portal-frame kit then runs 150–800 m²/day depending on crew size and complexity — the crew assumption matters more than the number.
In detail
Published erection rates disagree honestly — 500–800 m²/day (Laotie, 5-person crew) against 150–300 m²/day (JA Steel, 6–10 crew) — because crew and building differ. Plan on the conservative figure and hold the difference as float.
Foundations are the buyer's parallel track: concrete poured and anchor bolts surveyed before the ship docks is what makes the erection rate real.
Questions buyers ask
FAQ
Are you a factory or a trading company?
HANJI Steel Structures is operated by Jiangsu Hanji Supply Chain Co., Ltd. — design and fabrication are our own work, from Cangzhou, Hebei. Products outside our line (specialist doors, refrigeration, fit-out) are named in the scope as coordinated supply.
Can I inspect before shipment?
Yes — your own visit or a third-party inspector (SGS, Bureau Veritas) at agreed hold points, before the balance is paid.
What does the price for a steel warehouse include?
Only what its scope line says: scope (frame, envelope or turnkey), basis (FOB, CIF or installed) and date are stated on every figure — the FOB vs CIF guide explains the ladder.