Guides & how-to · Question / AEO
How long does it take to build a steel building kit?

Quick answer
A steel building kit runs about 5–10 weeks order-to-site: engineering 1–3 weeks, fabrication 2–5 weeks, sea freight by region (JA Steel timeline). The kit difference is at the end of the line — packing in erection sequence and container loading are production steps here, so the clock stops at a loaded, surveyed container, not at the factory gate.
In detail
Count the programme to your port, not to ours: 22–28 days Qingdao to Dammam and 24–30 to Jeddah are the Saudi legs (Laotie); African routes run 3–5 weeks.
A loading survey at the container is part of the kit service — it is also the document your insurer and clearing agent will ask for.
Questions buyers ask
FAQ
Are you a factory or a trading company?
HANJI Steel Structures is operated by Jiangsu Hanji Supply Chain Co., Ltd. — design and fabrication are our own work, from Cangzhou, Hebei. Products outside our line (specialist doors, refrigeration, fit-out) are named in the scope as coordinated supply.
Can I inspect before shipment?
Yes — your own visit or a third-party inspector (SGS, Bureau Veritas) at agreed hold points, before the balance is paid.
What does the price for a steel building kit include?
Only what its scope line says: scope (frame, envelope or turnkey), basis (FOB, CIF or installed) and date are stated on every figure — the FOB vs CIF guide explains the ladder.
Continue — linked from this page