Bay Spacing — the 3–7% Cost Lever

Steel building — Bay Spacing — the 3–7% Cost Lever
DESIGN VISUALISATION

Quick answer

Bay spacing — the distance between portal frames — quietly moves a building's cost by about 3–7% (Promisteel PEB cost guide, 2026): wider bays mean heavier purlins and fewer frames; narrower bays mean more frames and more foundations. The optimum sits where frame, purlin and foundation costs cross, and finding it is free at design stage.

The design note

This is the first value-engineering conversation to have — before value-cutting anything visible.

Price it exactly

For this size the planning figures are bay spacing moves total cost by roughly 3–7% (Promisteel, 2026) — on optimisation saves real tonnes at Optimised per span. They are starting points with sources named, not a quotation: run your exact dimensions through the calculator for a first estimate on the same method, then send the brief for an itemised quotation with the tonnage and kg/m² stated for your building, your cladding scope and your port.

Questions buyers ask

FAQ

Are you a factory or a trading company?

HANJI Steel Structures is operated by Jiangsu Hanji Supply Chain Co., Ltd. — design and fabrication are our own work, from Cangzhou, Hebei. Products outside our line (specialist doors, refrigeration, fit-out) are named in the scope as coordinated supply.

Can I inspect before shipment?

Yes — your own visit or a third-party inspector (SGS, Bureau Veritas) at agreed hold points, before the balance is paid.

What does the price for this size of building include?

Only what its scope line says: scope (frame, envelope or turnkey), basis (FOB, CIF or installed) and date are stated on every figure — the FOB vs CIF guide explains the ladder.

Continue — linked from this page