How to install a cold storage building — erection sequence and crew

Quick answer
Cold storage erection builds the frame as a warehouse, then slows down at the envelope: panels set with continuous vapour sealing, joints taped and sealed as they close, insulated doors hung and adjusted as finished units. The envelope is the machine — a cold store's erection quality is measured at the seals, not at the steel.
In detail
Floor insulation and the slab interface are sequenced before panel closure — retrofitting under a sealed envelope is the expensive version.
Hold an inspection point at envelope completion, before refrigeration fit-out hides the seals forever.
Questions buyers ask
FAQ
Are you a factory or a trading company?
HANJI Steel Structures is operated by Jiangsu Hanji Supply Chain Co., Ltd. — design and fabrication are our own work, from Cangzhou, Hebei. Products outside our line (specialist doors, refrigeration, fit-out) are named in the scope as coordinated supply.
Can I inspect before shipment?
Yes — your own visit or a third-party inspector (SGS, Bureau Veritas) at agreed hold points, before the balance is paid.
What does the price for a cold storage building include?
Only what its scope line says: scope (frame, envelope or turnkey), basis (FOB, CIF or installed) and date are stated on every figure — the FOB vs CIF guide explains the ladder.