How long does it take to build a sandwich panel building?

Quick answer
A sandwich panel building runs on the frame programme — engineering 1–3 weeks, fabrication 2–5 weeks — with the panels produced in parallel to the specified core and thickness. The panel line, not the frame line, is where a late specification change costs weeks: core material and thickness are production inputs, not site decisions.
In detail
Fire-rated rock-wool and PIR panels at greater thicknesses are the usual long-lead variants; single-skin sheeting, by contrast, is a stock item.
Erection of a panelled envelope is fast but sequence-critical — panels arrive in wall order, and the packing list is written that way.
Questions buyers ask
FAQ
Are you a factory or a trading company?
HANJI Steel Structures is operated by Jiangsu Hanji Supply Chain Co., Ltd. — design and fabrication are our own work, from Cangzhou, Hebei. Products outside our line (specialist doors, refrigeration, fit-out) are named in the scope as coordinated supply.
Can I inspect before shipment?
Yes — your own visit or a third-party inspector (SGS, Bureau Veritas) at agreed hold points, before the balance is paid.
What does the price for a sandwich panel building include?
Only what its scope line says: scope (frame, envelope or turnkey), basis (FOB, CIF or installed) and date are stated on every figure — the FOB vs CIF guide explains the ladder.