Guides & how-to · Question / AEO

How to install a sandwich panel building — erection sequence and crew

Steel building — a sandwich panel building
DESIGN VISUALISATION

Quick answer

Sandwich panel erection closes a framed building panel by panel: wall panels set plumb on the girts, fixed through or concealed per the system, joints sealed as they close; roof panels follow with closures and flashings. The craft is in the joints — a panel building's weather and thermal performance is the sum of its sealed seams.

In detail

Panels arrive in wall order from the packing plan; erecting out of order borrows panels from later walls and pays it back at the end.

Cutting on site is minimised by the panel schedule — openings are drawn, not discovered; verify door and louvre positions against the schedule before the first panel stands.

Questions buyers ask

FAQ

Are you a factory or a trading company?

HANJI Steel Structures is operated by Jiangsu Hanji Supply Chain Co., Ltd. — design and fabrication are our own work, from Cangzhou, Hebei. Products outside our line (specialist doors, refrigeration, fit-out) are named in the scope as coordinated supply.

Can I inspect before shipment?

Yes — your own visit or a third-party inspector (SGS, Bureau Veritas) at agreed hold points, before the balance is paid.

What does the price for a sandwich panel building include?

Only what its scope line says: scope (frame, envelope or turnkey), basis (FOB, CIF or installed) and date are stated on every figure — the FOB vs CIF guide explains the ladder.

Continue — linked from this page