Guides & how-to · Question / AEO

How long does it take to build a steel factory?

Steel building — a steel factory
DESIGN VISUALISATION

Quick answer

A steel factory follows the warehouse programme — engineering 1–3 weeks, fabrication 2–5 weeks, sea freight by region — with one addition: the crane. Runway beams and stiffer columns fabricate inside the same window, but the crane machine itself is usually a separate purchase with its own lead time; order it against the building programme, not after it.

In detail

Crane duty class is a design-freeze item: a late change from occasional to all-day lifting re-opens runway design and the fabrication slot with it.

Erection sequencing puts the runway in before cladding closes the bays — the process page shows the order the kit is packed in.

Questions buyers ask

FAQ

Are you a factory or a trading company?

HANJI Steel Structures is operated by Jiangsu Hanji Supply Chain Co., Ltd. — design and fabrication are our own work, from Cangzhou, Hebei. Products outside our line (specialist doors, refrigeration, fit-out) are named in the scope as coordinated supply.

Can I inspect before shipment?

Yes — your own visit or a third-party inspector (SGS, Bureau Veritas) at agreed hold points, before the balance is paid.

What does the price for a steel factory include?

Only what its scope line says: scope (frame, envelope or turnkey), basis (FOB, CIF or installed) and date are stated on every figure — the FOB vs CIF guide explains the ladder.

Continue — linked from this page