How to compare quotations for a steel factory without being misled

Steel building — a steel factory
DESIGN VISUALISATION

Quick answer

Compare factory quotations with the crane held constant: same capacity, same duty class, same runway scope in every bid — then tonnage, kg/m² against the 35–55 kg/m² crane band, coating and documents (HF Steel quotation guides). The commonest factory mis-comparison is a 5-ton occasional-duty runway priced against a 10-ton all-day one, wearing the same building dimensions.

In detail

Ask whether the crane machine itself is inside or outside each price — suppliers split on this, and the machine is not a rounding error.

Runway steel designed for different duty classes is invisible in a $/m² figure; the duty class must appear in writing.

Questions buyers ask

FAQ

Are you a factory or a trading company?

HANJI Steel Structures is operated by Jiangsu Hanji Supply Chain Co., Ltd. — design and fabrication are our own work, from Cangzhou, Hebei. Products outside our line (specialist doors, refrigeration, fit-out) are named in the scope as coordinated supply.

Can I inspect before shipment?

Yes — your own visit or a third-party inspector (SGS, Bureau Veritas) at agreed hold points, before the balance is paid.

What does the price for a steel factory include?

Only what its scope line says: scope (frame, envelope, or envelope with accessories), basis (FOB, CIF or installed) and date are stated on every figure — the FOB vs CIF guide explains the ladder.