Guides & how-to · Question / AEO

How to install a steel factory — erection sequence and crew

Steel building — a steel factory
DESIGN VISUALISATION

Quick answer

Factory erection adds the crane runway to the warehouse sequence: frames and bracing first, runway beams aligned and levelled while the bays are still open, then purlins, cladding and doors. The runway is surveyed as a machine bed, not as steelwork — alignment now is the crane's ride quality for thirty years.

In detail

The crane machine itself installs after the building is weathertight, by the crane supplier — sequence the two contracts so the runway survey is signed before the bridge arrives.

Erection rates run 150–800 m²/day by crew and complexity (JA Steel; Laotie); crane buildings sit at the careful end of that range.

Questions buyers ask

FAQ

Are you a factory or a trading company?

HANJI Steel Structures is operated by Jiangsu Hanji Supply Chain Co., Ltd. — design and fabrication are our own work, from Cangzhou, Hebei. Products outside our line (specialist doors, refrigeration, fit-out) are named in the scope as coordinated supply.

Can I inspect before shipment?

Yes — your own visit or a third-party inspector (SGS, Bureau Veritas) at agreed hold points, before the balance is paid.

What does the price for a steel factory include?

Only what its scope line says: scope (frame, envelope or turnkey), basis (FOB, CIF or installed) and date are stated on every figure — the FOB vs CIF guide explains the ladder.

Continue — linked from this page