How long does it take to build a steel structure?

Quick answer
A steel structure runs about 5–10 weeks order-to-site for standard types: engineering 1–3 weeks, fabrication 2–5 weeks, then sea freight of 1–2 weeks to Southeast Asia, 2–3 weeks to the Middle East or 3–5 weeks to Africa. Long-span, space-frame and multi-storey work sits above that band — engineered and scheduled per project.
In detail
Erection is the local half of the programme: published rates run 150–800 m²/day depending on crew size and complexity (JA Steel; Laotie), so the crew plan belongs in the schedule from the start.
The process page walks the nine production steps the fabrication window contains; the shipping guide covers the freight leg in the same detail.
Questions buyers ask
FAQ
Are you a factory or a trading company?
HANJI Steel Structures is operated by Jiangsu Hanji Supply Chain Co., Ltd. — design and fabrication are our own work, from Cangzhou, Hebei. Products outside our line (specialist doors, refrigeration, fit-out) are named in the scope as coordinated supply.
Can I inspect before shipment?
Yes — your own visit or a third-party inspector (SGS, Bureau Veritas) at agreed hold points, before the balance is paid.
What does the price for a steel structure include?
Only what its scope line says: scope (frame, envelope or turnkey), basis (FOB, CIF or installed) and date are stated on every figure — the FOB vs CIF guide explains the ladder.