How to install a labour camp — erection sequence and crew

Quick answer
Camp erection is repetition with a tape measure: the first block is set out, levelled and checked slowly — it is the template — and following blocks repeat at production pace with local crews. Light-gauge units need no heavy crane; services connect block by block, so occupation can phase behind the erection front as the workforce mobilises.
In detail
Set the first block's foundation tolerance tight: every repeated block inherits it, in both directions.
SBC 801 facility ratios are checked at layout, but sanitation and fire systems are commissioned block by block — plan the commissioning sequence with the erection one.
Questions buyers ask
FAQ
Are you a factory or a trading company?
HANJI Steel Structures is operated by Jiangsu Hanji Supply Chain Co., Ltd. — design and fabrication are our own work, from Cangzhou, Hebei. Products outside our line (specialist doors, refrigeration, fit-out) are named in the scope as coordinated supply.
Can I inspect before shipment?
Yes — your own visit or a third-party inspector (SGS, Bureau Veritas) at agreed hold points, before the balance is paid.
What does the price for a labour camp include?
Only what its scope line says: scope (frame, envelope or turnkey), basis (FOB, CIF or installed) and date are stated on every figure — the FOB vs CIF guide explains the ladder.
Continue — linked from this page