How long does it take to build a PEB building?

Quick answer
A PEB building runs about 5–10 weeks order-to-site: engineering 1–3 weeks, fabrication 2–5 weeks, sea freight 1–2 weeks to Southeast Asia, 2–3 to the Middle East or 3–5 to Africa (JA Steel timeline). The pre-engineering is the point: connection details and section families are standardised, so design time buys optimisation, not invention.
In detail
The programme assumes the design inputs freeze at approval drawings; every post-approval change re-opens both the engineering and the fabrication queue.
Certificates and approvals — SABER for Saudi, civil-defense routes in the UAE — run in parallel when planned at quotation; remembered late, they become the critical path.
Questions buyers ask
FAQ
Are you a factory or a trading company?
HANJI Steel Structures is operated by Jiangsu Hanji Supply Chain Co., Ltd. — design and fabrication are our own work, from Cangzhou, Hebei. Products outside our line (specialist doors, refrigeration, fit-out) are named in the scope as coordinated supply.
Can I inspect before shipment?
Yes — your own visit or a third-party inspector (SGS, Bureau Veritas) at agreed hold points, before the balance is paid.
What does the price for a PEB building include?
Only what its scope line says: scope (frame, envelope or turnkey), basis (FOB, CIF or installed) and date are stated on every figure — the FOB vs CIF guide explains the ladder.
Continue — linked from this page